Class of 2013 - Promise House - Construction Update

Ten months ago the 2013 class held its final class session and graduation ceremony. At that point, we had raised over ten thousand dollars, and were still diligently working to finish construction documents for the new shelter space at Promise House. Through hard work, dedication, and help from some great partners in the industry (Beck and Balfour Beatty), the end is in sight!
 
September 8, 2014 marked a major milestone stone for Promise House, as interior construction officially began on the build out of additional shelter space for their teen center.
 
In just 5 short days, the 1,600 sf space had stud walls in place, and electrical work started. Day 9, electrical and plumbing was moving ahead full speed. Inspections for framing are next on the list, and should happen next week. This means drywall can start being installed next.
 
All duct work, air handlers, furnaces, and heat pumps are all in place - I hear the AC will be turned on today if all goes well! Plumbing is in and tied to the risers, and sprinkler heads are being relocated as this is written.
 
Next week, we should have rooms that actually start to look like rooms - equipped with drywall and lighting! After that, the space should be on the home stretch. Add some finishes, a little paint, furniture, and Promise House will have the additional space they need to house more teens.
 
The shelter will house 10 new beds for teens between the ages of 18-22, who have had a hard time getting on their feet and need a little help, support, and guidance in order to lead successful lives. If you would like to contribute to a great cause, please visit http://promisehouse.org/how-to-help/ 
 
Please check back for updated pictures of the space.
 








 
contributed by Shannon Carpenter, AIA